Industrial power users want federal regulators to force a regional grid operator to let competitors bid on four new power lines.
Southwest Power Pool (SPP) skipped competitive bidding on about $3.8 billion in transmission projects by wrongly labeling them short-term reliability fixes, the Electricity Transmission Competition Coalition and the Industrial Energy Consumers of America alleged in an Oct. 28 complaint to the Federal Energy Regulatory Commission (FERC). SPP’s answer is now due Dec. 17 after FERC pushed back the deadline, according to a Nov. 16 notice.
“By using the need date that cannot be met to preclude competition, SPP is losing the benefit of competition without a legitimate reason,” the coalition wrote in comments to SPP that the complaint quotes.
“Rto’s [regional transmission organizations] do not have any accountability to ratepayers … and incumbents have too much influence over the RTOs,” Paul Cicio, president and CEO of the Industrial Energy Consumers of America, told the Daily Caller News Foundation in a statement.
The coalition speaks for companies that consume electricity, but its members also include think tanks and “non-incumbent transmission developers,” according to the complaint.
Transmission rates are “the fastest growing part of consumer electricity bills,” the complaint states.
SPP’s rules let it hand a project straight to the local utility only if the project is “required to be in service within three years or less to address an identified reliability violation,” the complaint states. None of the four lines is scheduled to enter service before May 2029, according to the complaint.
One is a 239-mile line running from the Texas Panhandle into southeastern New Mexico. SPP said the line was needed by June 1, 2026, its December 2025 project report shows. That line is not scheduled to enter service before Nov. 18, 2030, according to the complaint.
The projects “have already been assigned and the Designated Transmission Owners are in the process of developing and/or constructing them,” SPP wrote in a Nov. 6 motion to FERC.
“There is no evidence Complainants will be harmed without Commission action before February 2027,” SPP wrote in the motion.
FERC closed an investigation into the exemption in 2020 after finding SPP still met its criteria, the grid operator noted in its motion.
The two groups waited nearly nine months after SPP’s board approved the designations to file, the grid operator argued in a Nov. 12 filing.
“SPP is aware of the complaint that has been filed at FERC regarding short-term reliability projects and is currently reviewing it,” the grid operator said in a statement to the DCNF.
It will keep following its tariff rules so the projects are “constructed in a timely manner to keep the lights on,” SPP said.
Xcel Energy, which owns Southwestern Public Service Company, did not respond to a request for comment. Oklahoma Gas and Electric (OG&E) did not provide a comment on the record.
The four projects would cost $3.78 billion, SPP’s report shows. About $2.37 billion of that is for a 315-mile line from central Oklahoma to northwest Louisiana.
FERC’s Order No. 1000 took away utilities’ first crack at building lines picked in regional plans, the commission’s summary states. It did not make regions take bids.
“Even a 20 percent reduction in the approximately $3.8 billion of proposed investment would represent $760 million in savings,” the Conservative Energy Network, which backs the complaint, wrote on Wednesday.
The group calls itself dedicated to free-market energy policy. It warned that such estimates “should not be interpreted as guaranteed savings for the projects at issue.”
OG&E offered to give up its return on equity on whatever it spends on the Oklahoma-Louisiana line beyond 20 percent above the estimate in SPP’s notice to construct, according to testimony from Jay Caspary of TransGrid Advisors, a witness for the complainants.
“Foregoing return on equity for costs 20% above a figure you get to name, with no outside competitive pressure to offer the lowest dollar amount possible, does not robustly incentivize aggressive cost reductions for customers,” Caspary wrote.
New Mexico’s Public Regulation Commission asked FERC to keep the cost of delay in mind. Drillers in the state’s slice of the Permian Basin still cannot hook their wells up to the local utility, so they run them on diesel and gas generators, the commission wrote on Wednesday.
For the New Mexico line, “speed to power is imperative,” the commission added. It said it “does not take the position that an extended construction schedule negates the reliability need itself” but also cautioned that “potential delay does not excuse noncompliance.”
The report blames fast load growth and weak ties to the rest of SPP. Southwestern Public Service’s expected load jumped from about 4,700 megawatts to 11,500 megawatts between the 2023 and 2025 planning cycles, nearly 150 percent, it shows.
More than 57,000 outage scenarios in SPP’s models for the area would not solve, which the report says could mean voltage collapse.
SPP later cut the area’s forecast by 11 percent to 20 percent, but the reliability concerns “remain largely unchanged,” the report states.
SPP’s board approved the four designations on Feb. 3. That same day it backed an effort “to maintain and improve the competitive bid framework,” meeting minutes show.
The groups are asking FERC to find that SPP broke its tariff. They also want all four lines put out for bid, according to the complaint.
(DCNF)