The Kwara State government has recorded zero spending from its ₦5billion 2026 budget allocation for school infrastructure despite the fact that pupils across the state have continued to learn in dilapidated classrooms, under leaking roofs and makeshift shelters.
SaharaReporters’ examination of the Kwara State Government’s 2026 Third Quarter (Q3) Budget Performance Report showed that the state government allocated ₦5billion for a programme described as “adequate infrastructure at all levels”, but recorded zero spending against the allocation between January and September 2026.
The report, which covers January to September 2026, put the performance of the programme at zero per cent, leaving the entire ₦5billion allocation unspent as of the end of the third quarter of the year.
The allocation falls under the education sector’s programme classification and is specifically identified as code 0505: Adequate Infrastructure at All Levels.
The report did not explain why the ₦5 billion infrastructure allocation recorded no expenditure, whether the projects were delayed, whether procurement processes have been completed, or whether the government has encountered implementation challenges.
Meanwhile, from classrooms with collapsed ceilings and broken windows to pupils receiving lessons under makeshift shelters, public schools in Kwara State are battling deteriorating infrastructure, raising serious concerns over the state government’s commitment to addressing the worsening condition of public schools.
The revelation is particularly concerning against the background of reports of deteriorating public school facilities across different parts of the state, where pupils and teachers have to contend with damaged classrooms, inadequate furniture, overcrowding, leaking roofs and other conditions that undermine effective learning.
At Warah Community Junior Secondary School in Ilorin West Local Government Area, it was reported in March 2026 that pupils were receiving lessons in crumbling classrooms, makeshift shelters and an unfenced school compound.
The school has classrooms with collapsed ceilings, exposed and deteriorating wooden supports, peeling paint and broken windows.
Some pupils were reportedly forced to receive lessons under makeshift structures constructed by community members using wooden frames, tarpaulin and old roofing sheets.
Others reportedly sat on bare floors because of inadequate classrooms and furniture.
The school was also reported to have an overcrowded learning environment, with community sources estimating that at least 300pupils were either sitting on bare floors or attending lessons under temporary shelters.
The school’s sanitation facilities were also a major concern, with community members reportedly describing its only toilet as barely functional.
Media reports mentioned a member of the school’s education committee, Alhaji Isiaka Warah, as saying that the community has repeatedly written to relevant authorities seeking intervention but has yet to receive the necessary response.
At Government Day Secondary School, Lafiagi, in Kwara North, there were reports of dilapidated classrooms in the Universal Basic Education section and a staff room reportedly without a ceiling, fan or windows.
Renovation work on senior secondary classroom blocks and the examination hall, which reportedly began in 2025, was said to have remained uncompleted.
The unfinished work reportedly left some senior students without dedicated classrooms, forcing different groups to share available spaces, including science laboratories, for lessons.
There have also been reports on the condition of Government Day Secondary School, Fate, in Ilorin East Local Government Area, particularly on leaking and collapsing classrooms, stolen roofing sheets, a lack of functional toilets, and the absence of essential learning facilities, including a standard science laboratory and library.
A teacher in the school reportedly said that only two classrooms in the senior secondary section were in relatively better condition, following renovation by old students.
The school’s old students also lamented that former students have been forced to intervene in renovating classrooms and providing facilities that should ordinarily be maintained by the government.
The Teaching Service Commission chairman has also reportedly acknowledged the poor condition of the school’s classrooms but claimed that the government was planning a renovation.
At Ojoku Grammar School in Oyun Local Government Area, there were report of deteriorating buildings, collapsing classrooms and inadequate learning facilities.
It was gathered that a federal intervention intended to provide additional classrooms has not been fully delivered according to the original project scope.
Although two blocks of two classrooms were reportedly expected under the revised contract, it was gathered that only one block of two classrooms has been completed.
There were reports of cracking floors and deteriorating furniture in the completed structure, raising concerns about the quality of the work.
These reports provide identifiable examples of the infrastructure challenges facing public schools in different parts of Kwara State, amid which, the state government recorded zero spending from its ₦5 billion school infrastructure budget allocation.
The state government’s own budget implementation figures added another dimension to the concerns.
According to Table 27 of the 2026 Third Quarter Budget Performance Report, the government approved ₦5 billion for the “Adequate Infrastructure at All Levels” programme.
However, the report recorded zero expenditure against the allocation between January and September, representing zero per cent budget performance.
The report also showed that the Ministry of Education and Human Capital Development has a separate ₦5 billion allocation under the administrative classification, against which no expenditure was recorded during the same period under review.
At the broader programme level, the education component of the social sector has an approved allocation of ₦5.749 billion but recorded only ₦218.85 million in expenditure in the first nine months of the year.

The Kwara State Universal Basic Education Board recorded ₦218.85 million in expenditure from its ₦749.13 million allocation, representing 29.2 per cent performance, while the Ministry of Education and Human Capital Development recorded zero expenditure against its separate ₦5 billion budget allocation.
The figures raise questions about how the state intends to address the infrastructure challenges confronting public schools when a major allocation specifically approved for improving education facilities has not been utilised by the end of third quarter of the year.
The report also showed that the Ministry of Education and Human Capital Development has a separate ₦5 billion allocation under the administrative classification, but recorded no expenditure against that allocation during the period under review.

The figures appear more concerning when viewed against the state’s stated education objectives, which include expanding access to education, improving retention and completion rates, promoting equity and inclusiveness, improving teaching and learning outcomes, and providing adequate infrastructure.
The Governor AbdulRahman AbdulRasaq administration had previously announced plans to increase investment in school infrastructure.
In August 2025, the state government announced a ₦20 billion allocation in a supplementary budget for school infrastructure upgrades across the state’s 16 local government areas.
The Commissioner for Education and Human Capital Development, Dr Lawal Olohungbebe, said the intervention would target dilapidated facilities, classroom shortages, laboratories and sanitation facilities.
The government also said more than 1,254 classrooms had been upgraded since 2019.
However, the 2026 third-quarter budget implementation report figures raise questions about the implementation of the separate ₦5 billion infrastructure programme and how much of the promised investment has translated into improved facilities in schools still experiencing serious infrastructure challenges.
For families who cannot afford private education, public schools remain an essential route to education for their children.
But when classrooms have damaged ceilings, inadequate furniture, leaking roofs and insufficient sanitation facilities, pupils are left to bear the consequences of infrastructure failures they have no power to correct.
Teachers also face the challenge of delivering lessons in overcrowded and poorly equipped environments, while communities and old students are sometimes compelled to raise funds to renovate buildings and provide basic facilities.
The contrast between the reported conditions in some schools and the zero expenditure recorded against the ₦5 billion infrastructure allocation raises an urgent accountability question: why was the money not spent during the first nine months of the year, when documented infrastructure needs remained?
The report does not explain why the allocation recorded zero expenditure, whether procurement or implementation processes stalled, or whether the planned projects were delayed.
It also does not establish that no school rehabilitation took place elsewhere in the state during the period.
For a child attending a public school, budgetary allocations are not merely figures in government documents.
They are expected to translate into classrooms that do not expose pupils to unsafe conditions, functional toilets, adequate learning spaces and facilities that make education worthwhile.
When billions of naira earmarked for infrastructure remain unspent for nine months, the consequences of delayed implementation are borne not by officials who approve budgets, but by pupils, teachers and parents who depend on the public education system.
For pupils studying in classrooms with damaged ceilings, broken windows and inadequate facilities, explanations about budgetary processes are not enough.
They need safe classrooms, functional toilets, adequate furniture and an environment where learning can take place without avoidable hardship.